References
Basic School of Podolinec
Commencement and completion date:
06.2009 - 09.2009
Invoiced price: 991 405 EUR
Project: weatherproofing, reconstruction of sanitary facilities, boiler house, classrooms, floors, wiring
Basic School of Spisska Stara Ves
Commencement and completion date:
06.2009 - 09.2009
Invoiced price: 630 638 EUR
Project: weatherproofing, reconstruction of sanitary facilities, floors, wiring, wall paintings
Basic School of Jakubany
Commencement and completion date:
12.2009 - 08.2010
Invoiced price 958 493 EUR
Project: weatherproofing, reconstruction of sanitary facilities, boiler room, floors, classrooms, main building annexe - third floor
Basic School of Jesenske
Commencement and completion date:
03.2010 - 08.2010
Invoiced price: 418 863 EUR
Project: Weatherproofing
Gymnasium of Roznava
Commencement and completion date:
11.2009 - 08.2010
Invoiced price: 295 574 EUR
Project:New multifunction gym - supply and installation of bricked vertical constructions
Basic School of Zemplinska Teplica
Commencement and completion date:
10.2010 - 04.2011
Invoiced price: 490 085 EUR
Project: Complex reconstruction of school building
Ondrej Nepelu Hockey Arena Bratislava
Commencement and completion date:
03.2010 - 02.2011
Invoiced price: 315 505 EUR
Project: supply and installation of bricked vertical constructions
High School of Kralovsky Chlmec
Commencement and completion date:
03.2011 - 06.2011
Invoiced price: 100 500 EUR
Project: weatherproofing
Municipality of Gerlachov
Commencement and completion date:
11.2010 - 06.2011
Invoiced price: 310 562 EUR
Project: Revitalization of town centre
Municipality of Gerlachov
Commencement and completion date:
11.2010 - 06.2011
Invoiced price: 35 208 EUR
Project: Town sewerage
City of Puchov
Commencement and completion date:
04.2011 - 07.2011
Invoiced price: 363 973 EUR
Project: Cultural and educational centre - project in progress
Hotel Helpa
Commencement and completion date:
03.2011 - 12.2011
Invoiced price: 119 639 EUR
Project: Rebuilding of hotel
Toyota Auto-centre Zvolen
Commencement and completion date:
06.2011 - 12.2011
Invoiced price: 248 500 EUR
Project: Rebuilding of centre